Power task
A power task executes an action when the measured power of a meter meets a configured condition.
📋 Overview
With a power task an action is triggered based on the live measured power of a selected meter. You define the source, comparator, and threshold value, and configure what action is performed when the condition is met.
🎛️ Possibilities
Type
You set what type of task you are adding. In this case Power.
Condition
You set at what measured power the task is triggered:
- Source: Select the meter whose power is monitored. Meters are grouped by type:
- Energy suppliers: Grid connection points (PAP/SAP) or meters that act as such.
- Consumers/generators: Meters that measure both consumption and generation.
- Consumers: Meters that measure consumption only.
- Generators: Meters that measure generation only.
- Phases (multi-phase meters only): Select which phases (L1, L2, L3) are included in the measurement.
- Operation (consumers/generators only): Choose whether consumption or generation is measured:
- For grid connection points: Importing or Exporting.
- For batteries: Charging or Discharging.
- For other meters: Consuming or Generating.
- Power: Set the threshold value (in watts). The task is triggered when the measured power meets the chosen comparator: less than (
<), less than or equals (<=), equals (=), not equals (!=), greater than or equals (>=), or greater than (>).
Action
You choose an actuator or automation on which the task performs an action. The available actions depend on the actuators and automations available in the installation.
Tariff switcher:
- Tariff: Set the tariff to Low/Off-peak or High/Peak.
Switches:
- State: Select the desired state. Depending on the type of switch, different states are possible, e.g. Off, On, Normal, High, Max.
- Keep in this state for a minimum duration: Enable this to keep the device in the selected state for at least a set duration. Other tasks cannot change the state during this lock period. Set the Minimum duration (in minutes).
Power curtailment:
- State: Select the desired state for power curtailment (Off, On).
- Power: When enabled, set the desired power using the slider (0–100%).
Charge/discharge control:
- State: Select the desired state for the battery (Off, Discharge, Charge).
- Power: When discharging or charging, set the desired power using the slider (depending on the battery capacity).
Automations:
- State: Select whether the automation becomes Active or Paused.
📝 Managing tasks
Adding a power task
- Go to Tasks within your installation.
- Click
+ Addto add a new task. - Select Power as the type and click
Next. - Select the source, configure phases and operation if applicable, and set the comparator and threshold value. Click
Next. - Select the desired actuator or automation.
- Configure the desired action based on the selected actuator or automation.
- Click
+ Createto save the task.
Editing a task